Wastewater Facility & Collection System Master Plan Update

Project Update: The current master plan is 17 years old and this project will update the City wastewater facility and infrastructure master plan. The master plan is an infrastructure needs analysis to deliver adequate sanitary sewer collection, treatment, and effluent discharge for a 20 year planning period. This project is funded by the Sewer SDC Fund.

Location: City Wide

Status:  City Council public hearing tentatively scheduled for December but subject to change. DEQ requires permit modification to go to EQC. Master plan revivision underway due to EQC requirement by DEQ.

Schedule: Public hearings scheduled for December 2018

Updated:  November 1, 2018

Contractor: Dyer Partnership

Cost Estimation: $241,000

Master Plan Documents: See supporting documents below.